Works and Repair Contracts in Bulgaria

We help with contracts with craftsmen, renovation firms and builders: from agreeing the price and deadlines to accepting the work and disputes over defects.

In short

What can I do if renovation work in Bulgaria is late, defective or unpaid?

We draft and review contracts for works, renovation and finishing works, and we protect both clients and contractors when work is late, defective or unpaid. You get a clear assessment of what you can claim and how to prove it. The first consultation is free of charge.

Renovating a flat, having furniture made or building a house are deals where the dispute often starts with the agreement itself. The price is 'approximate', the deadline is 'within a month', and nobody wrote down what exactly is included. Bulgarian law calls this a contract for works (договор за изработка, Art. 258 of the Obligations and Contracts Act, ЗЗД): the contractor undertakes, at its own risk, to make something according to the order, and the client undertakes to pay for it.

We work for both sides: owners who need protection against delay and poor work, and craftsmen and firms who have not been paid. Call or write to us before you sign the contract, or as soon as a problem appears.

What to agree in a renovation contract

A good works contract describes the work so precisely that, at handover, there is no argument about what should have been done. As a contract lawyer in Sofia, we recommend that the contract contains at least:

  • A detailed description of the works, quantities and materials, ideally with a bill of quantities attached.
  • The price: a lump sum for the whole job or unit prices, and when it may change.
  • Who supplies the materials and who bears the risk if they are damaged.
  • Start and end dates, and interim stages.
  • Payment in stages, each linked to acceptance of that stage.
  • A penalty for delay and a warranty period.

Can a builder raise the price during the renovation?

It depends on what was agreed. The law gives the contractor no right to change the agreed price on its own. If, however, the price was agreed as unit prices, the final amount is set at acceptance according to the quantities actually done (Art. 266(1) of the Obligations and Contracts Act) and may exceed the initial estimate. That is why the estimate should be attached to the contract, with a clause that any increase in quantities or price must be approved in advance and in writing.

What to do if the builder is late

If the work is late, first send a written reminder with a new, reasonable deadline. If a penalty for delay was agreed, it starts to accrue on the first day after the deadline. When signing, pay attention to its size: details are on our penalties and interest page.

If the contractor does not finish within the new deadline either, you can terminate the contract by giving it a reasonable period with a warning that the contract will then be considered terminated (Art. 87 of the Obligations and Contracts Act). How this works and what is returned afterwards is explained on our termination for breach page.

Can I cancel the contract before the work is finished?

Yes, if there are good reasons. The client may withdraw even after the work has started. The client then pays the contractor its expenses, the work done and the profit it would have made (Art. 268 of the Obligations and Contracts Act). If the contractor is in breach, termination is the better route, because then you do not owe its lost profit.

Accepting the work: the handover report and objections

The client must accept the work if it has been done according to the contract. On acceptance the client should inspect it and point out any visible defects. If you accept the work without comments, it will later be hard to argue that obvious defects already existed then.

That is why acceptance is recorded in a written handover report listing every comment, with photos if needed. Hidden defects that appear later should be reported to the contractor as soon as you discover them, again in writing.

What can I do if the renovation work is poor quality?

If the work was done with deviations or defects, you can ask for them to be repaired free of charge within a reasonable time, for the cost of the repair to be paid to you, or for the price to be reduced (Art. 265 of the Obligations and Contracts Act). If the defects are so serious that the work is unfit for its purpose, you can terminate the contract. You can also claim compensation for your loss.

Can I withhold payment from the builder?

In a bilateral contract each party may refuse to perform until the other performs its own obligation (Art. 90 of the Obligations and Contracts Act). The client may withhold payment for work that is unfinished or defective. This must be proportionate: withholding the whole price over a minor comment can turn against you.

If the contractor has finished and handed over the work properly and the client does not pay, the contractor can claim the price and statutory interest for late payment. See also our breach of contract claim page.

Do I have to pay for extra work I did not order?

As a rule you pay for what you ordered. Extra work is agreed separately, ideally in writing and with a price. If you accepted it and are using the result, the dispute becomes more complicated. So agree in the contract that every change must be approved in writing, including by email or message.

How to prove poor-quality work

In a dispute the strongest evidence is a court-appointed technical expert report. An expert inspects the site and reports on the quantity and quality of the work and the cost of repairs. So do not have the defects fixed by another builder before you have documented them: photos, video, an inspection report and, if needed, an independent inspection.

Keep the contract, the invoices, the payment documents and all correspondence, including messages in apps. Paying by bank transfer with a reference that matches the contract prevents arguments about how much was paid.

What documents should you prepare?

  • The contract, the offer or the bill of quantities
  • Payment documents: invoices, receipts, bank transfers
  • Handover reports and the comments on them
  • Dated photos and video of the defects
  • Correspondence with the contractor, including messages in apps
  • Quotes from other firms for repairing the defects

Who will handle your case

Frequently asked questions about works and repair contracts

Is an oral agreement with a builder valid?

Yes. As a rule the law does not require a written form for a contract for works. Without a written contract, however, it is hard to prove what was ordered, at what price and by when, so we recommend at least a short written agreement.

How much of an advance is reasonable to pay?

The law does not set an amount. It is sensible for the advance to cover the materials for the first stage, with the rest paid after each stage is accepted. That way there is always an unpaid part that motivates the contractor to finish.

What happens to my advance if the builder disappears?

If the work has not been done, you can terminate the contract and ask for the advance back together with compensation for your loss. It is important to prove how much you paid and what part of the work was done.

Is the contractor liable if a defect appears a year later?

It may be, if the defect was hidden at acceptance and is reported as soon as it is discovered (Art. 264(2) ЗЗД). The client's rights for defects, however, expire after six months, or after five years for construction works (Art. 265(3) ЗЗД). For buildings the warranty periods under Ordinance No. 2 of 2003 also apply, and an agreed warranty period may give you extra protection, so do not delay taking action.

The builder damaged a neighbouring property. Who is liable?

Towards the neighbour, the contractor and the client are usually liable depending on the cause of the damage. The contract should say who bears liability for damage to third parties and whether the contractor is insured.

Can you help me if I am the contractor and the client does not pay?

Yes. We also represent craftsmen and firms. We collect the price owed through a demand, order-for-payment proceedings or a lawsuit, and where the client objects to the quality we respond with handover reports, correspondence and expert evidence.