Appealing a Demolition Order in Bulgaria

We object to the statement of findings within 7 days, appeal the demolition order within 14 and seek suspension of preliminary enforcement, before the administrative court and the Supreme Administrative Court.

In short

How do I appeal a demolition order in Bulgaria?

We defend owners whose houses, extensions, garages or storeys are the subject of a statement of findings or a demolition order from the municipality or the Directorate for National Construction Control (ДНСК). We prepare the objections, the appeal to the administrative court and the request to suspend preliminary enforcement, and represent you before the Supreme Administrative Court too. The first consultation is free of charge.

With a demolition order, everything is decided in a few days: 7 for objections to the statement of findings (констативен акт), 14 for an appeal against the order, and only 3 if the authority has allowed preliminary enforcement. In those days the authority's competence and the description of the building must be checked, evidence gathered and, if needed, suspension requested. A missed deadline usually cannot be put right, and a demolished building cannot be restored.

As spatial planning lawyers in Sofia, we take the case from the first document to the court's judgment. Send us the statement or the order on the day it is served on you.

Statement of findings for unlawful construction: objections within 7 days

A demolition order is issued on the basis of a statement of findings drawn up by the building control officers (Art. 225a(2) of the Spatial Planning Act, Закон за устройство на територията, ЗУТ). The statement is served on the interested parties, who can file written objections within 7 days. This is the cheapest and often the most important moment for your defence, because anything you do not raise then is hard to prove later.

In the objections we check whether the description of the building matches reality and which item of Art. 225(2) of the Spatial Planning Act is relied on, and we attach the documents: permit, designs, legalisation act, tolerance certificate, evidence of the year of construction. If the building may date from before 31 March 2001, tolerance is covered on the page on legalising a building.

Can the statement of findings be appealed?

In practice the statement of findings is usually treated as a preparatory document that cannot be appealed to the court on its own. A written objection with a reference number is therefore the only way to influence the authority before the order. If construction is still ongoing, the authority also issues a stop order, and an appeal against it does not suspend enforcement.

Who issues a demolition order: the mayor or ДНСК

Competence depends on the building's category. For category IV to VI buildings (houses, holiday homes, garages, canopies and most extensions) the order is issued by the mayor of the municipality or district, or by an official the mayor has authorised (Art. 225a(1) of the Spatial Planning Act). For category I to III buildings, the head of the Directorate for National Construction Control (ДНСК) is competent (Art. 225(1)).

An order issued by an authority without competence is liable to be annulled (Art. 146, item 1 of the Administrative Procedure Code, Административнопроцесуален кодекс, АПК). That is why we always check the category, the authorisation order and the legal basis. Not every removal order is under Art. 225 or 225a: movable structures under Art. 57a and dangerous buildings under Art. 195–196 of the Spatial Planning Act follow other rules, and an appeal does not suspend enforcement.

Can only part of a building be demolished?

Yes. The order may cover only the unlawful part: an extension, an additional storey or a canopy. Sometimes voluntarily removing that part saves the rest of the building and unlocks a new permit on the plot.

Appealing a demolition order: deadline, court and evidence

The appeal is filed within 14 days of service, through the authority that issued the order, not directly with the court (Art. 215(4) of the Spatial Planning Act). The case is heard by the administrative court where the property is located, and its judgment can as a rule be appealed to the Supreme Administrative Court within 14 days. We calculate deadlines with the legal deadline calculator too, but we never leave filing to the last day.

The authority must prove the facts on which it based the order (Art. 170(1) of the Administrative Procedure Code). In practice, though, cases are most often decided by the court-appointed technical expert: what exactly was built, which category it falls into, whether it complies with the plan and roughly when it was built. We prepare the questions for the expert and the witnesses. A table of the stages and deadlines is in our article on demolition orders in Bulgaria.

Does it matter that the building is my only home?

It may. In Simonova v. Bulgaria (2023) the European Court of Human Rights found a violation because neither the authority nor the court had assessed whether demolishing a family home was proportionate. Bulgarian courts' case law on this argument is not consistent and it does not make the building lawful, but when it is well grounded it can carry weight.

Suspending enforcement of a demolition order

An appeal filed in time as a rule suspends enforcement (Art. 166(1) of the Administrative Procedure Code), because orders under Art. 225 and 225a of the Spatial Planning Act are not among the acts listed in Art. 217(1) whose enforcement an appeal does not suspend. Until the order enters into force, the building cannot be demolished.

The exception is when the authority has allowed preliminary enforcement. That direction is appealed within 3 days of service (Art. 60(5) of the Administrative Procedure Code), and the court can suspend enforcement until it rules (Art. 60(6)). We show that there is no urgency: the building has stood for years and endangers no one.

What if the building is demolished and the order is later annulled?

What remains is a claim for compensation against the municipality or the state under the State and Municipalities Liability for Damage Act (Закон за отговорността на държавата и общините за вреди, ЗОДОВ). How such a case works is explained on the page on claims against the state. Compensation does not bring the building back, though, which is why the 3-day deadline is the most important in the whole procedure.

Enforced demolition: who pays

If an order that has entered into force is not complied with voluntarily, the municipality or ДНСК demolishes the building itself (Art. 225a(3) and Art. 225(4) of the Spatial Planning Act). On the basis of the order and the record of costs, an order for immediate enforcement under Art. 418 of the Civil Procedure Code (ГПК) is issued, and the costs are collected through a bailiff.

The person who built, the client who commissioned the work and the construction supervisor are jointly and severally liable, and in certain cases so are the builder, the designer and the consultant who assessed the design (Art. 225a(5)–(6) of the Spatial Planning Act). Voluntary removal usually costs less: you choose the contractor and can keep the materials.

What documents should you prepare?

  • The statement of findings and the order, with the date each was served on you
  • The title document for the property
  • Building documents: permit, approved designs, legalisation act, tolerance certificate
  • Evidence of the year of construction: electricity and water contracts, tax returns, photographs
  • Photographs of the building in its current state
  • A notarised power of attorney, if you live abroad

Who will handle your case

Frequently asked questions about demolition orders

Do I have to be in Bulgaria for the case?

No. A lawyer can file the appeal and represent you under a power of attorney. It is important that someone keeps an eye on the property, because when the builder is unknown, copies of the statement and the order are posted on the building itself and at designated places in the municipality.

When does the appeal deadline start to run?

From the date the order is served on you, not from its publication in the Unified Public Register for Spatial Planning. Note the date of service and seek advice the same day.

What happens if I send the appeal straight to the court?

The law requires the appeal to be filed through the authority that issued the order. Sending it directly to the court is one of the most common mistakes and creates an unnecessary dispute over the deadline, so we file the appeal the correct way.

Will I be fined as well as having the building demolished?

Possibly. A participant in construction who carries out, orders or allows unlawful construction is liable to a fine of EUR 511.29 to 5,112.92 (BGN 1,000–10,000), unless another law provides a heavier penalty (Art. 232(2) of the Spatial Planning Act). The penalty decree is appealed separately.

I bought the property recently. Does the order affect me?

Yes. The order concerns the building, and as the owner you defend yourself within the same deadlines. Any claims against the seller over the unlawful extension are a separate matter and can be brought in separate proceedings.

Can I build again on the plot after demolition?

Yes, with an approved design and a permit under the normal procedure. Until the unlawful structure is removed, the person who built it is not issued a permit for new construction on the plot (Art. 148(7) of the Spatial Planning Act).

Planning and Construction Lawyer in Sofia

Have a legal question? Get in touch.

The initial consultation is free and without obligation.